Bagger 16-9

New hydraulic excavator in use.

The civil work activities at the Unterentfelden site have had a new mobile excavator since January. It was possible to put the vehicle, which has a lifting capacity of up to 1,500 kg, to immediate use in the excavation work undertaken as part of a sewer diversion. 

Carolin Rabea Primerova 1-1
16.02.2020
Author Carolin Rabea Primerova

New hydraulic excavator in use.

A sewer line in Kölliken runs right through four new building lots. For this reason, the municipality decided to move the line closer to the parcel boundary and the access road. The trenches in which the sewage pipes were to run again had already been excavated by the cablex Unterentfelden civil work team. The newly acquired hydraulic excavator was used to perform this work. The eight-tonne vehicle is roadworthy and equipped with the latest engine Technology.

The pipes have to be laid very precisely.

"The challenge in the construction of sewage systems is adhering to the pipe gradient," said Samuel Schaffner, Head of Department Network Planning & Construction. "The pipes have to be laid very precisely, so that the wastewater can flow away unimpeded," explains Schaffner.

Main sewer pipes are usually laid with a gradient of 0.5 to 2.4 per cent. The height of the inlet and the outlet is already set (by the previous course of the pipe).

After the diversion of the sewage system, the gradient of the line is only 1.03 per cent. This corresponds to a slope of 1.03 cm per metre.

Personen im Schacht 16-9

Alignment of the gradient.

The pipes have to be put into the trench with absolute precision in order to ensure that the pipe has a continuous gradient. Before the new sewer pipe is put into the trench, a layer of envelope concrete is put into the bottom of the trench.

Two concrete blocks serve as fixed points for the alignment of the gradient. The correct position of the blocks is determined using a laser measuring device.The audio signal of the laser indicates whether the concrete blocks are at the correct height. The longer the signal sounds, the more accurately the height of the block corresponds to the target. The envelope concrete bottom is aligned to the gradient with the concrete blocks as orientation.

Ausmessen 16-9

Proper alignment is also crucial for connecting the already laid pipe to the newly embedded pipe. Thanks to the correct position, the two pipe sections can be joined together. Before laying the pipe, it must be ensured that the inside of the pipe is clean. The rubber gaskets and the sleeve must be tight to withstand the pressure test that will be conducted later. For the pressure test, water is fed into the pipe, and the amount of water loss is measured.

Excavator operator with finesse.

Pipes of this size and weight are difficult to connect together manually. The hydraulic excavator is used by the excavator operator with a great deal of finesse to connect the inserted pipe to the already installed pipe. Here, the excavator has to apply pressure to the sewer pipe as accurately as possible in the alignment direction. The motto here is: "As little as possible, but as much as necessary." If the excavator operator exerts too much pressure on the pipe, he risks damaging the sleeve at the joint end. In this case, the next pipe cannot be connected.

To make matters worse, the shovel of the excavator has to operate in the excavator operator's blind spot. Seamless teamwork is called for here. The excavator operator must be able to rely on the instructions of his colleagues in the trench. Finally, the pipe is covered with envelope concrete. The concrete must harden sufficiently, so that it does not crack later.

Rohr 16-9
Schutzmatte 16-9

In cold weather, a protective mat is put on so the concrete does not freeze. Only a clean pipe bedding ensures that the pipe can later accommodate the pressure when the trench is filled. Once the diversion of the sewage system is complete, the manholes are constructed and the utility lines (e.g. electricity, telephone) are laid in the road, the road construction will be tackled. In this phase of construction, the granite edging is set, driveways are built and the asphalt layer is paved.

Ein Monteur installiert die INFRABOX

The INFRABOX makes mobile communication systems intelligent.

The smart little box enables digital remote reading and control of the infrastructure and facilitates maintenance.

Carolin Rabea Primerova 1-1
Three cablex employees who work flexibly for the company.

How ‘performing together’ works in Ticino

The small region in the south is particularly reliant on the flexibility of its employees.

Carolin Rabea Primerova 1-1
cablex Mitarbeiter lädt sein E-Fahrzeug

E-cars for a better environment: the sustainable strategy of cablex.

Our cablex workforce is already travelling to customer locations in a very sustainable manner with almost 1,000 electric vehicles.

Martina Strazzer 1-1
Beleuchtete Autobahn bei Nacht_24-9.jpg

Transport.

Creating a future-proof infrastructure with cablex.

24-9 Ausbau E-Ladestation Header

cablex is expanding the charging infrastructure for electric vehicles at all locations.

cablex is expanding the charging infrastructure for electric vehicles at all its locations – a service that we also offer externally to our customers.

Larissa Mihalik 1-1
Portes ouvertes Header 24-9

Open house day - bienvenue à Penthalaz!

On 20 and 21 September, cablex opened its doors at the Penthalaz site to customers, partners, interested parties, employees and their families.

Larissa Mihalik 1-1
3-4 kopa

Plan construction projects sustainably and save costs.

Das Ziel ist, sich zukünftig mit anderen Unternehmen abzusprechen und die Rohre für Wasser, Energie und Telekommunikation in einem gemeinsamen Bauvorhaben zu realisieren.

Carolin Rabea Primerova 1-1
cablex Academy 24-9

cablex Academy.

The cablex Academy teaches specialist skills (competences) in the fields of network construction, service and installation. Here, focus is on the area of network construction for telecommunication.

Hero Smart Meter 24-9

Intelligent energy meters from smart cablex.

Smart meters make it possible to check electricity consumption remotely at any time

Wladimir Kiselew im Rosenbergtunnel

cablex handles complex switchovers in the Rosenberg tunnel.

Tunnel renovations are part of daily operations of the infrastructure segment of cablex AG. Cablex was responsible for the preliminary measures in the Rosenberg tunnel in St. Gallen.

Carolin Rabea Primerova 1-1
Im Rahmen eines Pilotprojektes stattete cablex in den letzten Monaten Swisscom Zentralen mit Photovoltaikanlagen aus.

Customised photovoltaic expansion for Swisscom central offices.

As part of a pilot project, cablex has equipped Swisscom control centres with photovoltaic systems in recent months.

Carolin Rabea Primerova 1-1

cablex AG

Tannackerstrasse 7

3073 Gümligen

cablex.info@cablex.ch

0800 222 444