Second drone pilot case from cablex.

In July 2021, we reported on our pilot project Transportation of materials with the help of drones. We have now carried out the second trial, whereby the cargo drone transported 1,100 kilos of radio material onto a building. This flight was also successful and brought us plenty of new insights.

Martina Strazzer 1-1
14.10.2021
Author Martina Strazzer

The location for this drone flight was a grain silo in Olten in Solothurn Canton. This drone mission required somewhat more extensive preparatory work than the first pilot test. Once the permits had been obtained from FOCA, we of course wrote to all the businesses in the area around the test site to inform them of our plans. Following this, the test site was cordoned off and secured in line with regulations and measures were taken to ensure that only those involved in the project were present on site.

Second drone pilot case from cablex.

The use case.

The drone flew 1,100 kilos of radio material onto a 50-metre-high grain silo for an upgrade of a Swisscom antenna system. The grain silo in Olten is a “site-share location”, which means there are antenna systems belonging to various telecoms providers there.

Drohnenpilot 2: Personen vor der Last
Drohnenpilot 2: Drohne mit Antenne

The transport.

Sixteen flights were required to transport the 1,100 kilos of heavy material onto the silo directly next to the antenna mast. Transport time for all these flights alone amounted to 160 minutes, to which must be added the time taken for setup on the ground to ensure the drone was safe and carrying the permitted weight.

The objective.

Currently, helicopters are often used for transportation of antenna equipment in rough terrain and mountainous areas. These tasks could also be assumed by cargo drones in the future. The objective of this drone flight was to improve the processes, times and coordination, to enable us to get close to the current standard operation with helicopters.

Further pilot tests.

The pilot phase is to be continued over the next few months. Among other things, plans are in place to transport material directly to the technician on the antenna. We are working wholeheartedly and with dedication to evaluate all the findings and monitor further developments in the market. Our goal is to apply new technologies in areas where they can make everyday tasks easier and are economical.

Ein Monteur installiert die INFRABOX

The INFRABOX makes mobile communication systems intelligent.

The smart little box enables digital remote reading and control of the infrastructure and facilitates maintenance.

Carolin Rabea Primerova 1-1
Three cablex employees who work flexibly for the company.

How ‘performing together’ works in Ticino

The small region in the south is particularly reliant on the flexibility of its employees.

Carolin Rabea Primerova 1-1
cablex Mitarbeiter lädt sein E-Fahrzeug

E-cars for a better environment: the sustainable strategy of cablex.

Our cablex workforce is already travelling to customer locations in a very sustainable manner with almost 1,000 electric vehicles.

Martina Strazzer 1-1
Beleuchtete Autobahn bei Nacht_24-9.jpg

Transport.

Creating a future-proof infrastructure with cablex.

24-9 Ausbau E-Ladestation Header

cablex is expanding the charging infrastructure for electric vehicles at all locations.

cablex is expanding the charging infrastructure for electric vehicles at all its locations – a service that we also offer externally to our customers.

Larissa Mihalik 1-1
Portes ouvertes Header 24-9

Open house day - bienvenue à Penthalaz!

On 20 and 21 September, cablex opened its doors at the Penthalaz site to customers, partners, interested parties, employees and their families.

Larissa Mihalik 1-1
3-4 kopa

Plan construction projects sustainably and save costs.

Das Ziel ist, sich zukünftig mit anderen Unternehmen abzusprechen und die Rohre für Wasser, Energie und Telekommunikation in einem gemeinsamen Bauvorhaben zu realisieren.

Carolin Rabea Primerova 1-1
cablex Academy 24-9

cablex Academy.

The cablex Academy teaches specialist skills (competences) in the fields of network construction, service and installation. Here, focus is on the area of network construction for telecommunication.

Hero Smart Meter 24-9

Intelligent energy meters from smart cablex.

Smart meters make it possible to check electricity consumption remotely at any time

Wladimir Kiselew im Rosenbergtunnel

cablex handles complex switchovers in the Rosenberg tunnel.

Tunnel renovations are part of daily operations of the infrastructure segment of cablex AG. Cablex was responsible for the preliminary measures in the Rosenberg tunnel in St. Gallen.

Carolin Rabea Primerova 1-1
Im Rahmen eines Pilotprojektes stattete cablex in den letzten Monaten Swisscom Zentralen mit Photovoltaikanlagen aus.

Customised photovoltaic expansion for Swisscom central offices.

As part of a pilot project, cablex has equipped Swisscom control centres with photovoltaic systems in recent months.

Carolin Rabea Primerova 1-1

cablex AG

Tannackerstrasse 7

3073 Gümligen

cablex.info@cablex.ch

0800 222 444